THIRD QUARTER REVIEW AND ANALYSIS
DEPARTMENT OF PUBLIC WORKS
CITY OF SALISBURY, MARYLAND
1. PRINCIPAL FUNCTIONS (See First Quarter R & A)
2. ANNUAL OPERATIONS (See First Quarter R & A)
3. F.Y. 2004 GOALS (See First Quarter R & A)
4. PROBLEMS AND CORRECTIVE ACTIONS
A. Industrial Discharges and Pretreatment Program
1. The new NPDES permit took effect September 1, 2004.
2. A local limits study is currently underway.
3. Design for the plant upgrade to BNR is ongoing.
4. The vacant Pretreatment Technician position has been filled
5. Fuji Sushi Bar has been issued a Compliance Order for Fats-Oils-Grease problems.
6. The vacant Assistant Pretreatment Coordinator position has been advertised and should soon be filled.
B. Wastewater Treatment Plant
1. Overall compliance for the quarter ( January, February ) was 100.0 %.
2. Violations for the quarter:
January 2005 – Zero permit violations this month, 100.0 %
February 2005 – Zero permit violations this month, 100.0 %
March 2005 – info not available yet
C. Septage Handling Program
1. The Septage Facility is open and receiving septage.
2. The septage fee charged to septage haulers for the City to receive treat, store, and land apply residential septage generated within Wicomico County is currently set at $66/1,000 gallons. The fee for out-of-county is the same.
|
|
KWH |
GREASE |
HAULER |
|
TOTAL |
CITY |
WICO |
|
Month |
Used |
GALLONS |
GALLONS |
TICKETS |
FEES |
SHARE |
SHARE |
|
Jan |
10112 |
7500 |
19100 |
35 |
$1,155.00 |
$1,120.00 |
$35.00 |
|
Aug |
8832 |
3400 |
24975 |
45 |
$1,485.00 |
$1,440.00 |
$45.00 |
|
Sept |
7392 |
9,200 |
34,925 |
64 |
$2,112.00 |
$2,048.00 |
$64.00 |
|
TOTALS: |
26336 |
20100 |
79000 |
114 |
$4,752.00 |
$4,608.00 |
$144.00 |
D. Biosolids Department
1. Worked on permitting tree farm in Worcester County for sludge application. Made presentations to local groups on tree farm application of treated sewage sludge.
2. Ran beltpress for plant weekly sludge and dewatering of lagoon #4 and decanted lagoons as needed.
3. Prepared for spring hauling schedule.
4 Limed fields as needed.
5. Took delivery of new diesel decant (bypass) pump.
LIQUID BELTPRESSED
Sludge Hauled: Jan None None
Feb None 3.1 dt
Mar 200,000 gal None
---------------------------------------------------------------------------------------------------------------
County leachate: Jan Data not in gallons
(To City system) Feb " gallons
Mar " gallons
---------------------------------------------------------------------------------------------------------------
. Days Storage: Working: 11.4 days @ 18,000 gpd as of 3-24-05
Reserve: 1 days @ 18,000 gpd 3-24-05
E. Laboratory Services
|
Analysis for Wastewater Treatment Plant Process Control: |
|
||||||
|
|
|
|
|
|
January |
February |
March |
|
1. Biochemical Oxygen Demand (BOD ) |
|
84 |
74 |
85 |
|||
|
2. pH measurements |
|
84 |
74 |
85 |
|||
|
2. Total Suspended Solids |
|
|
57 |
52 |
58 |
||
|
3. Total Phosphorus and Orthophosphate |
|
41 |
38 |
40 |
|||
|
4. Fecal Coliform |
|
|
|
26 |
24 |
28 |
|
|
5. Sludge: |
|
|
|
|
|
|
|
|
|
% Solids |
|
|
|
42 |
38 |
55 |
|
|
% volatile |
|
|
|
38 |
29 |
44 |
|
6. Digester: |
|
|
|
|
|
|
|
|
|
Volatile Acids |
|
|
16 |
20 |
34 |
|
|
|
Alkalinity |
|
|
|
16 |
20 |
34 |
|
|
Bicarbonate Alkalinity |
|
16 |
20 |
34 |
||
|
|
Ratio: V. Acids/ Bicarbonate Alkalinity |
16 |
20 |
34 |
|||
|
|
pH |
|
|
|
16 |
20 |
34 |
|
7. Ferric Chloride |
|
|
|
4 |
3 |
3 |
|
|
|
|
|
|
|
|
Bacteriological and Chemical Analysis for Drinking Water Monitoring and |
|||||||
|
Corrosion Control. |
|
|
|
|
|
|
|
|
|
|
|
|
|
January |
February |
March |
|
1. Fecal Coliform |
|
|
|
26 |
26 |
26 |
|
|
2. Heterotrophic Plate Count for bacteria density |
26 |
26 |
26 |
||||
|
3. pH |
|
|
|
|
26 |
26 |
26 |
|
4. Total Chlorine |
|
|
|
26 |
26 |
26 |
|
|
5. Free Chlorine |
|
|
|
26 |
26 |
26 |
|
|
6. Total Iron |
|
|
|
26 |
26 |
26 |
|
|
7. Total Phosphorus |
|
|
|
26 |
26 |
26 |
|
|
8. Total Hardness |
|
|
|
26 |
26 |
26 |
|
|
9. Total Alkalinity |
|
|
|
26 |
26 |
26 |
|
|
10.Chloride |
|
|
|
26 |
26 |
26 |
|
|
11. Langelier Indices |
|
|
|
26 |
26 |
26 |
|
|
12. Aggressive Indices |
|
|
26 |
26 |
26 |
||
|
13. Manganese |
|
|
|
26 |
26 |
26 |
|
|
14. Sulfate |
|
|
|
26 |
26 |
26 |
|
|
15. Total Dissolve Solids ( TDS ) |
|
|
26 |
26 |
26 |
||
5. GENERAL FUND ACTIVITIES
Citywide Curb, Gutter and Sidewalk
Contract No. A -7-03: 86% Complete
Contract No. A-7-04: 94% "
Contract No. A-7-05: 23% “
Citywide Blacktop
Contract No. 9-03-BT- Blacktop- 60% Complete
Contract No. 9-04-BT- Blacktop- 83% Complete
Contract No. 9-05-BT- Blacktop- 100% Complete
Pavement Millings
Contract No. 8-04-PM- 91% Complete
6. SEWER FUND ACTIVITIES
7. WATER FUND ACTIVITIES
A. Installed security fences around the water towers and reservoirs
B. Lead and copper testing has been completed and incompliance
C. Clean-out for Edgemore and College Ave. elevated storage tanks completed as of July 2003
D. Phase I - Scada System is 90% complete
E. Electrical upgrade for the Park Water Plant is complete and fully functional.
8. STORMWATER MANAGEMENT
|
|
QUARTER |
|||
|
|
1 |
2 |
3 |
4 |
|
• Plans Reviewed |
24 |
20 |
26 |
|
|
• Plans Approved |
9 |
5 |
5 |
|
|
• Waivers Granted |
0 |
0 |
0 |
|
|
• Inspections Performed |
12 |
17 |
16 |
|
9. PRELIMINARY DEVELOPMENT PROJECTS
|
500 Riverside Drive |
|
Accelerated Autosports (Kiley Dr.) |
|
Advanced Auto Parts (W. Ruark Dr. & Rt. 13 N.) |
|
Adylotte Farm (Beaglin Park Drive) |
|
Allen Memorial Church |
|
Aspen Hills (Dykes Road) |
|
Avalon Retirement Community |
|
Avalon Shopping Center, Lot B Talbots |
|
Avalon Shopping Center, Lot C, Courtyards by Marriott, (Dickerson Lane) |
|
AWB Expansion (Northwood Drive) |
|
Aydelotte Farm |
|
Belmont Crossing (East Park Professional Center) |
|
Briarcliff (Dykes Road) |
|
Causey/Carey property ( Snow Hill Rd.) |
|
Cedar Crossing II (Onley Road) |
|
Centre @ Salisbury (Regal Cinema) |
|
Courtesy Chevrolet (North Salisbury Blvd.) |
|
Culver Mini Storage (Pemberton Drive) |
|
Datile Flooring Phase II (Northwood Drive) |
|
Delmarva Professional Center (John Deere Drive) |
|
Eastern Shore Mini Storage (Kiley Drive) |
|
Eireann M'hor (Kilarney Dr.) |
|
Farlow Farm ( Old OC Rd.) |
|
First St. closing |
|
Frieda-Potts Property ( Rt. 50 West) |
|
Glen Heights (Glen Avenue) |
|
Harbor Pointe Phase 4 & 4A |
|
Hertigate (Pemberton Drive) |
|
Hickory Lane One Go-Getters (Calloway St.) |
|
Hotel (W. Zion Rd.) |
|
Interfaith Housing (W. Naylor Mill Rd.) |
|
Jasmine Dr. |
|
John Deere Condominiums (John Deere Drive) |
|
John Deere Dr. lot 4-A |
|
Johnson's Retreat ( Johnson Rd.) |
|
JR Enterprises (Winfield Ave. ) |
|
Kohl's ( W. Dagsboro Rd.) |
|
Layton's Mini Storage (E. Naylor Mill Rd.) |
|
Leonard Lane, lots A and B |
|
Linens to Go (Marvel Rd.,) |
|
Lord Salisbury Hotel Property (N. Salisbury Blvd.) |
|
Mall Renovation (Civic & Glen Ave.) |
|
Marriott Hotel (W. Zion Road) |
|
Martin's Mill (Dagsboro Road ) |
|
Merritt Mill Apts. (Merritt Mill Rd.) |
|
Metro Center East (Hobbs Road) |
|
Mill Pond Village Plaza (E. Naylor Mill Road) |
|
Millers Edge (Pemberton Dr.) |
|
Nolan Property (S. Division St.) |
|
North Salisbury School Expansion (Emerson & Union Ave.) |
|
North Salisbury Shoppes (Starbucks N. Salisbury Blvd.) |
|
Northgate Business Park Lot 3BBB (Northgate Drive) |
|
Oasis Car Wash (Hampshire Rd. ,) |
|
Pemberton Ponds (Pemberton Dr.) |
|
Phillip Morris Dr. Business Park (Phillip Morris Dr.) |
|
PRMC Expansion (Waverly Drive) |
|
Rite Aid (Parsons Road) |
|
River's Edge (Fitzwater Street) |
|
Robertson Farm (Ocean City Rd., Sharen Dr.) |
|
Royal Farm Store (Parsons Road) |
|
Salisbury Auto Body (Rt. 13 N.) |
|
Salisbury Mall Re-development |
|
Sassafras Meadows (West Road & Queen Avenue) |
|
Shady Grove (Dykes Road) |
|
Shopper's World - 2002 Redevelopment (Tilghman Rd.) |
|
Shore Distributors (Brown St.) |
|
Sorrells (Northwood Dr.) |
|
Stephens Property (Chelsea Court ) |
|
Stonegate Phase V (N. Schumaker Drive) |
|
The Fountains (Lot 7) |
|
The Fountains (lot 9A) |
|
The Fountains (Pigg, Krahl & Stern) |
|
The Preserves at Adylotte Farm, (Middle Neck Dr.) |
|
Three Creeks (W. Naylor Mill Rd.) |
|
Tim Mar Acres (John Deere Drive) |
|
Tractor Supply (E. Northpointe Drive) |
|
Trice Valuation Services (Mt. Hermon Rd.) |
|
University Village (Onley Road) |
|
Verizon (American Legion Rd.) |
|
Vernon Esham Property (Onley Road) |
|
Villages @ Parsons Lake (E. Naylor Mill Rd.) |
|
Villages @ Sleepy Hollow (Pemberton Drive) |
|
Wali Plaza (Parsons Rd.) |
|
Waterside Apts. (Parsons Rd.) |
|
Waterside East (Canal Park Dr .) |
|
Westside Manor (West Rd.) |
|
Westwood Apts. (West Rd.) |
|
Westwood Commerce Park |
|
Wicomico Transit (E.S. Adkins) |
|
Woodbrook (Tilghman Rd.) |
|
Woodcock Property (Caroline Street) |
|
Wyatt Mini Storage (Parsons Rd.) |
10. SPECIAL PROJECTS
Culver road - drainage design - Concept Design Completed
DPW and Planning & Zoning coordination of development and subdivision requirements
Evaluation of odor control, BOD removal and sludge disposal methods to be completed with BNR upgrade (construction completion scheduled for 2007
Final
design for WWTP BNR upgrade and expansion is underway including a
solids handling study to develop an alternative approach for sludge -
dewatering and sludge stabilization facilities to eliminate the need for
existing sludge-storage lagoons and sludge-thickness tanks and improve
sludge-disposal options and flexibility.
Johnson-Snow Hill Road Regional Storm Drain
Pretreatment program ongoing
Sludge management application/permits ongoing
11. PRELIMINARY SUBDIVISION/RESUBDIVISION/EASEMENT PLATS
|
Aspen Hills - Subdivision (Dykes Road) |
|
Aydelotte Farm - Subdivision (Beaglin Park Drive) |
|
Black Dog - Easement (Isabella St.) |
|
Briarcliff - Subdivision (Dykes Road) |
|
Donald Layton Mini storage - Easement (E. Naylor Mill) |
|
Eastern Shore Mini Storage - Resubdivision(Kiley Drive) |
|
Eireann Mh'or - Subdivision (Kilarney Drive) |
|
Farlow Farm - Resubdivision (Old Ocean City Road) |
|
Forest Lake Estates Lots 107,108 - Resubdivision (Emerson Avenue) |
|
Glen & Debra Wood lots 5-10 and 13A - Resubdivision (Windsor Drive) |
|
Go Getters - Subdivision (Calloway Street) |
|
Johnson's Retreat - Subdivision (Johnson Road) |
|
JR Enterprises - Resubdivision (Winfield Avenue) |
|
Layton Mini storage Easement - (E. Naylor Mill Rd.) |
|
Leonard Mill Lot 1A and 1B - Subdivision (W. Dagsboro Rd.) |
|
Lord Salisbury Shopping Center - Subdivision (Jasmine Dr.) |
|
Maguire/Dashill - Subdivision (East Railroad Ave.) |
|
Marley Manor - Easement (Robins Ave.) |
|
Marriott Hotel - Subdivision (W. Zion Road) |
|
Millers Edge - Easement (Pemberton Drive) |
|
Millers Edge -Subdivision (Pemberton Drive) |
|
North Salisbury School Expansion - Easement (Emerson Ave.) |
|
Northgate 10 Joint Venture - Resubdivision (Hampshire Road) |
|
Oasis Car Wash - Resub (Hampshire Rd.) |
|
Pemberton Ponds - Subdivision (Pemberton Drive) |
|
Pepsi cola - Resubdivision (Race Street) |
|
Phillip Morris Dr. Business Park - Resub (Phillip Morris Dr.) |
|
Ruark - Subdivision (East Naylor Mill Rd. ) |
|
Shady Grove - Subdivision (Dykes Road) |
|
Sharp Water- Resubdivision ( Columbia Road) |
|
Shopper's World - Subdivision (Tilghman Road) |
|
Stephens Property - Easement (Glen Avenue) |
|
Stonegate V - Resubdivision (N. Schumaker Drive) |
|
University Village - Easement (Onley Road) |
|
Villages @ Parson's Lake - Resub (Naylor Mill Rd. E.) |
|
Windsor Dr. lots 5-10 and 13A - Resubdivision (Windsor & Shipley Dr.) |
|
Woodbrooke Resubdivision (Tilghman Road) |
|
Woodcock Property - Easement (Hammond St.) |
12. ANNEXATIONS
Glen Avenue – Brown Property
Snow Hill Road – Causey & Carey
Brown Road – Ruark Property
Brewington Branch – Cannon Property
Pemberton Drive – Schneider Property
Mack Lane – University Park
South Division Street – Hearne Property
Parsons Road – G2 Property
Pemberton Drive – Crockett Property
Dagsboro Road – Faith Baptist Church
13. RIGHTS-OF-WAY AND EASEMENTS
New Subdivisions
Processing various deeds
Research in Land Records
14. LAND SURVEYS AND ACQUISITIONS
As-Built Surveys: Harbour Pointe - Water & Sewer
Mill Pond Village - Water, Sewer, and Stormwater
Stone Gate - Water, Sewer & Stormwater Management
Villages at Tony Tank Water & Sewer (Phase II)
Topo: Lake Street - Sewer Relief
Surveys: Molassas Branch – Riverside Road
Circle Ave & Market Street
W. Isabella Street – Utilities Yard
Pemberton Drive – Water Main Stakeout to WWTP
City Park – Md. Historical Trust Easement
Boundless Playground – Fence Easement Agreement
15. MISCELLANEOUS - SURVEYOR
Review subdivision plats and site drawings
Provide cadastral information to the public
City-owned land inventory completed
Public relations - land information and annexations
Logging field book index on computer
16. DESIGN/CONSTRUCTION PROJECTS
East Naylor Mill Road - Street lighting 100% complete
Northeast Collector - Construction is underway and is scheduled to end in October 2005.
Citywide combined sewer separation - Engineering for development of the long-term separation is underway.
17. TRAFFIC DIVISION
1. STP MAINT
2. WATER PLANT MAINT.
Checked out well house #1 pumps at Paleo
After flooding at well house # 1 checked out electrical equipment and sprayed with CRC 2-26 to displace water.
Helped contractor remove auto-start transformer and helped Jim install phase loss relays at well house #1
3. CITY YARD MAINT.
Replaced two fan motors in the bathrooms at the Utility Division
Installed antenna bracket on Operations Office Building
Checked outside receptacles at the Utility Yard
Installed service cable at the Utility Yard for new service
Installed new emergency generator
Repaired salt shed electric doors
Replace emergency light in Bay # 4
Reprogrammed bell time clock
Replaced sewer lift station cables
Made adjustments to limit switch for Street Dept. bay door
Replaced bulbs in Operations office area
Repaired security lights at the Traffic Shop
Replaced light bulbs at the Utility Yard
Installed conduits at the Utility Yard for communication cables
Installed heater in Parks Department office
Replaced bulbs in Stock Room
4. MARINA MAINT.
Repaired lights
Checked out hot water heater
5. ZOO MAINT.
Installed new service, receptacles, heater, and hot water heater and lights at the New Animal Education Facility.
Disconnected hot water heater
Installed conduit for Conectiv to provide service to the Animal Education Facility building
Checked out gas heater at the Visitor Center
Moved electric service for new location of lift pump station for office trailer
6. POLICE DEPT. MAINT.
Repaired three lights in parking lot
Disconnected wires to the emergency generator at the Police tower building
Replaced emergency light relay
Replace ballast in weight room
7. FIRE DEPT. MAINT.
Replaced breaker at Headquarters
Replaced eye on Headquarters security lights
8. SHOP MAINT.
Cleaned shop
Replaced blade in band saw
9. PARKING GARAGE MAINT.
Replaced two cobra heads on lot #1
Repaired light circuits on the top of Parking Garage
10. STREET LIGHT MAINT.
Made repairs on the following streetlights.
C.2 Terrie Ct. |
C.2 Dickerson |
C.2 Heron Ct. |
903 Walbash |
C.5 Healthway |
C.10 Cottontail Dr. |
C.4 Onley Dr. |
C.8 Brookridge |
C.42 ESD |
C.5 Mitchell Rd. |
C.4 South Park |
C.1 ESD |
C.5 Carroll St. |
C.1 South Park |
C.29 ESD |
C.12 Carroll St. |
C.30 ESD |
C.3 Healthway |
C.14 Carroll St. |
C.40 ESD |
207 Sandy Bottom Dr. |
C.6 Camden St. |
C.42 ESD |
C.2 Market St. |
C.8 Camden St. |
Parkwood |
C.2 Carroll St. |
C.4 Bantry Ln. |
C.1 Wayne |
C.3 Carroll St. |
Plaza |
C.4 Arthur Ct. |
Plaza |
Parking Lot #10 |
C.8 Adams |
C.3 Harden Ct. |
C.12 US 13 |
C.1 College Ln. |
C.1 Mitchell St. |
Walbash Dr. |
C. 16 Beaglin Pk. |
|
Village Oak Dr. |
C.8 Brookridge |
|
Repaired underground faults at the following locations.
Marvel Rd
Cypress St.
Did layout of street light installation on S. Clairmont Street
11. SIGNAL MAINT. & INSTALLATIONS
Made repairs at the following intersections
College Ave and Margaret
Beaglin Pk and Schumaker Dr
Division St and Main St
Beaglin Pk and Glen Ave
Camden and S. BLVD
Lake and Isabella
Long and E. Main
Carroll and Waverly
Installed switch and receptacle outlets for emergency generators and the following intersections.
Beaglin Pk and Glen Ave
Main St, Long Ave, Truitt, Mt. Harmon, and Williams St
Removed pole and flashing light service at E. Main and Davis St
12. SIGNS & POSTS
10 Riverside Dr. |
Brown St. (2) |
Goldsborough St. |
102 W. Chestnut St. |
Burton St. |
Green - Mor Av. |
111 High St. |
Camden Ct. |
Grier Av. |
219 North Blvd. |
Camden St. |
Hannibal St. |
233 Middle Blvd. |
Carroll St. |
Hazel Av. |
300 Locust Ter. |
Cedar Crossing |
High St. |
306 New York Av. |
Centenary Dr. |
Isabella St. (19 Flex posts) |
307 Middle Blvd. |
Church St. |
Lake St. (3) |
310 Locust Ter. |
Civic Av. |
Linwood Av. |
314 New York Av. |
Civic Center |
Lot 1 |
318 Locust Ter. |
Coles Cir. |
Lot 11 |
402 E. Vine St. |
College Av. |
Lot 15 |
419 South Blvd. |
Colonial Ct. |
Lot 33 |
643 Decatur Av. |
Crestview La. (3) |
Mack St. |
649 Decatur Av. |
Delaware Av. (2) |
Main St. (4) |
810 Church St. |
E. Chestnut St. |
Manor Dr. |
Alabama Av. |
E. Isabella St. (2) |
Market St. |
Alexander Av. |
E. Lincoln Av. |
Middle Blvd. |
Baker St. |
E. London Av. |
Middle Neck La |
Baker St. |
E. Main St. (2) |
N. Division St. |
Bateman St. |
E. Vine St. |
N. Park Dr. |
Beaglin Park Dr. |
Eastern Av. |
N. Division St. (2) |
Beaverdam Dr. (2) |
Eastern Shore Dr. (2) |
N. Park Dr. (3) |
Booth St. (2) |
Fitzwater St. |
N. Pinehurst Av. |
Broad St. |
Georgia Av. (3) |
N. Schumaker Dr. |
Object Markers (24) |
S. Park Dr. |
Truitt St. |
Ohio Av. |
Salisbury University (6 Signs) |
Vine St. |
Onley Rd. |
Salisbury Zoo |
W. Gordy Rd. |
Pearl St. |
Schumaker La. |
Ward Museum |
Phillip Morris Dr. |
Sharen Dr. |
Washington St. (2) |
Pinehurst Av. |
Smith St. |
Waverly Dr. (3) |
Priscilla St. |
Snow Hill Rd. |
White St. (2) |
Ridge Rd. (3) |
South Blvd. (2) |
Wicomico St. |
Riverside Dr. (8) |
Spring Av. |
Winder St. (2) |
Riverwalk Parking Signs |
Taylor St. (2) |
Windsor Dr. |
Roger St. |
Tokyo & Outback Steakhouse |
|
13. PAVEMENT MARKINGS
Carroll St.
S. Division St
Utilities - Paint Parking Space
14. LOCATES
Zoo |
Riverside Dr. |
Church St. |
Onley Rd. |
Pemberton Ct. |
Sweet Bay |
Terrapin Lane |
Ballinadee Dr. |
Industrial Parkway |
East North Pointe Dr. |
E. Naylor Mill |
Market St. |
W. Dagsboro Rd. |
Jasmine Dr. |
Utility Yard |
Troopers Way |
Cypress St. |
833 ESD |
1101 Monitor Ct. |
Naylor Mill Rd. |
Parsons Rd. |
144 E. Main Street |
W. Dagsboro Rd. |
Goldsborough St. |
1434 Ballinadee Dr. |
Harbor Pointe Dr. |
|
1020 Caravan Way |
Hobbs Rd. |
|
15. VEHICLE MAINT.
16. REPORTS and MEETINGS
Went to a Meeting about construction of Well House # 15
17. MISC.
Removed Christmas decorations
Carried the trencher to the Zoo for the Utilities Dept.
Helped Parks Dept. trim trees on North Park Dr.
Put up signs for road repairs on Isabella St.
Provided four inch 90’s for Conectiv job at Perdue Stadium
Blew in a pull line for Conectiv at Perdue Stadium
Checked out cable going across walk bridge in the park to make sure it was safe
Removed cables on Picnic Island for the removal of trees
Reinstalled cables to lights on Picnic Island
Replaced receptacle at US 13 Monument
Replaced light switch at Poplar Hill Mansion
Replaced light pole in the Park by the river
18.TRAFFIC STUDIES
Isabella St. and Division St
19.TRAINING
Purchasing Class
18. STREET DIVISION
Clean storm drains
Blacktopping city wide
Topsoiling & seed
Repair potholes citywide
Haul sweeper dump to landfill
Trash pickup at northwood area
Grading allies city wide
Pretrip & clean equipment
Snow removal
Place barricades & cones-functions
Built road. for wellhouse-E. Naylor Mill
Backfilled new Zoo building
Repaired greenway in park
Special bulkpickup week
19. PARKS BRANCH
1. Finish leaf removal on all city streets.
2. Attended chainsaw safty class in Chestertown.
3. Maintain city sidewalk in snow storm 1/19/05 to 1/20/05.
4. Maintain city sidewalk in snow storm 1/24/05 to 1/27/05.
5. Patched pot holes in streets after storm 2/1/05 to 1/4/05.
6. Cleared fences at water towers ,wellhouses and paleo waterplant.
7. Maintain city sidewalks in snow storm 2/24/05 to 2/25/05.
8. Edged all areas downtown.
9. Removed five dangerous trees at monument square.
10.Removed two dangerous trees on the greenway.
11.Contract for stump removal in park compete. (33)
12.Started mulching all city owned planters for the spring season.
13.Bulk trash the week of 3/28/05 to 3/31/05.
14.Picked up and recycled all city Christmas trees.
15.Planted 4000 bulbs thoughout city.
16.All park branch to Eastern Shore Commerical Pesticide Class on 2/8/05.
17.Maintain trash removal in river every week from marina to Rt.13.
20. CARPENTER SHOP
Repair doors at temporary zoo kitchen
Renovate interior of temporary zoo kitchen
Assist zoo personnel in relocation of equipment for temporary kitchen
Construct new Iguana cages for zoo
Assemble new benches for playgrounds
Assist Street and Parks Departments in snow removal
Construct display boards for Engineering
Repair finger pier at marina
Construct secure storage cabinet
Construct map boards for Street and Parks departments
Refurbish table and cabinets for Water and Sewer department
Assist in week-long bulk trash pickup
Prepare site and start construction of gazebo at Newton Street Tot Lot
21. UTILITIES
|
Sewer |
|
|
Jan |
Feb |
Mar |
|
new services |
|
4 |
0 |
3 |
|
|
renew services |
|
0 |
1 |
2 |
|
|
repaired services |
|
2 |
2 |
2 |
|
|
abondoned services |
|
0 |
0 |
1 |
|
|
service stoppages |
|
21 |
19 |
16 |
|
|
main stoppages |
|
6 |
5 |
7 |
|
|
main repaired |
|
0 |
0 |
0 |
|
|
manholes repaired |
|
3 |
2 |
2 |
|
|
chemicals |
|
|
6 |
1 |
2 |
|
misc/jobs |
|
|
0 |
0 |
0 |
|
|
|
|
|
|
|
|
Storm Drain |
|
|
|
|
|
|
main repaired |
|
0 |
0 |
0 |
|
|
inlets rebuilt |
|
0 |
0 |
0 |
|
|
inlets /new |
|
0 |
0 |
0 |
|
|
manholes rebuilt |
|
0 |
0 |
0 |
|
|
inlets repaired |
|
0 |
0 |
0 |
|
|
main stoppages |
|
1 |
0 |
2 |
|
|
inlet stoppages |
|
0 |
0 |
2 |
|
|
misc/jobs |
|
|
0 |
0 |
0 |
|
|
|
|
|
|
|
|
Water |
|
|
|
|
|
|
new services |
|
1 |
1 |
4 |
|
|
service renewals |
|
0 |
11 |
4 |
|
|
services repaired |
|
2 |
1 |
2 |
|
|
services abandoned |
|
4 |
2 |
2 |
|
|
hydrant repaired |
|
16 |
1 |
1 |
|
|
fire services installed |
|
0 |
1 |
1 |
|
|
mains repaired |
|
0 |
3 |
2 |
|
|
large meter change outs |
1 |
0 |
3 |
||
|
valve/vault adjustments |
2 |
7 |
2 |
||
|
misc/jobs: |
|
0 |
0 |
0 |
|
|
Coupon pits |
|
6 |
0 |
0 |
|
|
Miss utility locates |
|
207 |
224 |
381 |
|
22. WATER PLANT
Water pumped from: (January, February, March)
|
MAIN STREET WATER PLANT |
PALEO WATER PLANT |
|
TOTAL |
|||||
|
JANUARY |
52,403,410 |
|
JANUARY |
134,467,000 |
|
186,870,410 |
||
|
FEBRUARY |
56,936,285 |
|
FEBRUARY |
122,093,000 |
|
179,029,285 |
||
|
MARCH |
|
60,414,330 |
|
MARCH |
|
127,435,000 |
|
187,849,330 |
|
TOTAL |
|
169,754,025 |
|
TOTAL |
|
383,995,000 |
|
553,749,025 |
23. SALISBURY ZOO
Monthly Visitors Count:
January 2005 3,545
February 2005 3,955
March 2005 7,601
Total Visitor Count for Third Quarter – 15,101
American Zoo and Aquarium Association (AZA) Accreditation
Worked towards completion of List of Concerns from 2004 AZA inspection, including
major renovations to the Animal Services Building
Planning & Projects:
Continued construction of new Education Animal Facility
Presented Zoo Master Plan to Salisbury City Council, and to community
via PAC14 and zoo website
Started process for 2005 Strategic Plan for the Salisbury Zoo (contracted
with Dr. Memo Diriker and BEACON at Salisbury University)
Staff:
Hired Deborah Graham as a temporary zookeeper (filling in for Clement Grangier,
who is on Workmen’s Comp leave)
Education Report:
Trained 19 new Docents in March
Hosted all Dorchester County 4th Grade for forest ecology program
Received $4,800 grant from Chesapeake Bay Trust to conduct five “Wonders
of Water” teacher training workshops
Events:
Hosted Teddy Bear Brunch in February (earned $2,000)
Planned for Earth Day celebration in April
24. VEHICLE MAINTENANCE
|
Department |
Labor Hours |
Vehicle Parts Cost |
|
Engineer |
54 |
$ 502.27 |
|
Garage Miscellaneous |
0 |
$ 0 |
|
Operating & Maintenance |
186.5 |
$ 3,386.76 |
|
*Other Departments |
329.5 |
$ 1,894.26 |
|
Recycle |
7.5 |
$ 188.07 |
|
Sanitation |
123.5 |
$ 3,311.90 |
|
Sweeper |
26.5 |
$ 717.24 |
|
Traffic |
30 |
$ 571.20 |
|
Utilities |
190.5 |
$ 3,164.02 |
|
Water Treatment Plant |
1.5 |
$ 11.34 |
|
WWTP |
42.5 |
$ 1,390.80 |
|
Zoo |
10 |
$ 73.58 |
|
Total |
1002 |
$ 15,211.44 |
* Other Departments: Police, BHZ, and Purchasing Department