Processing Action
Team/Permitting Review
Site Plan Process Task
Force
Minutes of Meeting of December
6, 2006
Present:
Meeting Discussion Points:
1. Dale Pusey began discussion on Salisbury Public
Works’ site development plan review process.
a. The City has recently developed an inter-departmental
meeting to discuss site development requirements prior to annexation. Representatives of Public Works, Fire, Police
and Planning and Zoning departments present development concerns to the City
Administrator, John Pick. Those concerns
are made known to the property owner prior to annexation. It helps them see problems ahead of actually
going through the process.
b. The developer’s consultant submits a concept drawing
of the development plan showing layout of buildings, parking, entrances,
stormwater management and water, sewer and storm drainage. Submission of a concept drawing is
recommended but not required by Salisbury Public Works. The concept drawing by Public Works is
unrelated to Planning Commission review and approval. The concept drawing review by Public Works
results in a comment letter to the consultant that includes:
·
Guidance
regarding design of water, sewer and storm drainage. Includes oversizing requirements and layout
of public and private mains.
·
Explanation of
Comprehensive Connection Charges owed by the developer and possible
reimbursements that he may collect from future developers.
·
Explanation of
regional water, sewer, storm drainage and traffic improvements that may be
required and the developer’s estimated cost share of those improvements.
·
Regional storm
drainage and traffic study requirements.
·
Minimum
stormwater management quality control requirements.
Brock
Parker said that a concept phase gets the ball rolling. Matt Drew had the idea last week of making
this a required step. At first glance it
looks like it would extend the project because of it being an extra submittal,
but in the long run it would shorten the process. The reviewer wouldn’t have to spend as much
time going back through the plans and reviewing everything. It would also let the consultant know what
issues or problems he is going to face during the project up front. The concept plan should be submitted to the
City before preliminary plat approval.
Matt
Drew suggested allowing simple projects to bypass this phase. Have some kind of cut off that once exceeded a
concept phase is required. Brock
suggested requiring a concept phase for projects with a 15 acre or more
disturbance.
All
members of the group agree that a concept phase should be required. Dale asked if it should be required in the
preliminary stage of zoning, before the preliminary plat. Brock suggested that everything could be
turned in at the same time to Planning and Zoning and then they could give
Public Works their part. Dale said that
he wouldn’t want a concept phase to hold up Planning and Zoning, so it should
be an abbreviated review.
Dale
said that he would like to see Public Works held to what they put in writing
during the review. Matt agreed with that
and asked if there would be support for that.
Dale said he would like to say yes, but he is sure that it couldn’t be
guaranteed that things wouldn’t change.
David
Bates asked who would be responsible for doing the concept reviews. Would it be the reviewer who would have the
project in the other stages of the review?
Dale said that ideally it would be, but projects may get shifted as new
employees are hired.
c. The
developer’s consultant submits a preliminary fully engineered construction
improvements plan. The Salisbury Public
Works comment letter (P-1) is generated based on compliance with:
·
Information
contained in the concept letter.
·
City standards
and specifications.
·
City utility
design guidelines.
·
2000
The
project engineer coordinates his review comments with:
·
Salisbury Public
Work’s traffic engineer
·
Salisbury Public
Work’s wastewater pretreatment coordinator
·
·
Wicomico County
Public Works Department
·
d. Resubmitted
plan contains point-by-point response to P-1 and review comments are checked
off as they are resolved. This process
may take several iterations.
Matt
Drew said that he would like to see the comments separated for developers and
consultants, which was recommended in the PAT Recommendation Implementation
Plan from the last meetings. Brock said
that when he gets his comment letter he makes a list of comments that are just
for the developer. Dale asked if this
would be done in two letters. Matt said
it could be, just split them up and have a list of comments for each person.
Brock
said he would like to see a list of comments per page of the plan. That way the consultant would know exactly
where to look to fix the problem.
Matt
said sometimes the developer gets the comment letter and doesn’t realize that
anything in the letter pertains to him, so doesn’t bother reading it. David Bates said that the consultant needs to
get everything that the developer gets, so they know what has been sent.
Dale
said that having one letter is easier because all the comments are in one
place. He feels that splitting the
comments up into two letters would cause confusion. Matt suggested that it could be in one
document, but still separate the comments for the consultants and
developers. Dale said there could be a
third section for procedural comments.
2. Brock
brought up that there should be some kind of cut off for an endless stream of
revisions. Dale said that Public Works’
view on that is that the more that is found in the review stages, the less
problems there will be in the long run.
Brock felt that comments that are not important should not hold up the
review process.
David said
that he has a problem when new comments are found at each submittal that have
been missed in the previous reviews.
3. Brock
suggested that the grading permit be issued before the plat is recorded. Dale the grading permit can’t be issued until
the sediment control plan is signed. The
sediment control plan cannot be signed until the site plan is signed so the
grading permit can’t be approved early.
Matt
suggested adding a plan that only addresses the sediment control problems. If they created a sediment and erosion
control plan for the site, that could be approved ahead of the plat being
recorded and then grading permit could be issued.
Dale added
that there would need to be some kind of conditional approval. The developer would have to be willing to
take the risk of something coming up that needed to be changed during
construction. Dale will speak to Kevin
Keenan about having a conditional approval to get the grading permit issued earlier.
One
problem that Dale sees with issuing the grading permit early is that the City
would loose their leverage to get the deeds and plats recorded. Brock said that if the deeds and plats have
to be recorded before the Certificate of Occupancy is issued or the meters are
set, the City would still have their leverage, but construction could start
sooner.
4. Dale began
discussion of the last Recommendation Implementation Plan that was created in
2001 by the Development Process Action Plan (PAT).
Brock
suggested giving the consultant the option paying an extra fee to the City to
have the review of their project outsourced. Dale said the City will be
starting to outsource review, he is just not sure when that will start. Brock said that the reviewer should let the
consultant know if the review is expected to take longer usual (30 days). This would give the consultant the
opportunity to have the project outsourced if time is an issue.
David
asked if the whole project would be outsourced or if it would be broken into
parts and just outsource certain parts of the project. Everyone agreed that it should be the whole
project, breaking it into parts would cause confusion.
Brock
commented that the City couldn’t outsource right now because there isn’t
sufficient written guidelines and standards.
Dale disagreed; he felt that projects could be outsourced with the
current standards of the City of
Matt
asked if Dale felt the Public Works employees feel threatened by review being
outsourced. Dale said that they do.
Brock
suggested making outsourcing available only during times when the review will
take longer than the expected 30 days.
Dale said the City would have a list of pre-qualified consultants to do
the review. They would have to know in
the beginning how long it would take them, and hold the consultant to that time
frame. Brock said that would force the
reviewers of Public Works to speed up their review time.
Brock
suggested possibly accepting incomplete or incorrect plans as concept or
pre-preliminary plans and let the consultant know the once they fix the major
problems listed they would be accepted for full review.
Matt
suggested telling the consultant that the review stopped once these major
problems were found, and these issues need to be addressed before the review
can continue.
David
said that a meeting at that point would be helpful to show the consultant
exactly what the major problems are that need to be fixed before it can be
reviewed.
Dale
added that Public Works usually does provide a letter explaining why the plans
were rejected and comments on the major problems that have to be fixed before
the plans will be reviewed.
5. Due to the
time, Dale went through list of PAT Recommendation Summaries and indicated
which items were being implemented by Public Works.
·
Recommendation
#5—Speeding up the Review Process. See
5-A through 5-M.
·
Recommendation
#5-A—Goal of 30 days maximum to reject incomplete plans. Has been implemented by Public Works.
·
Recommendation
#5-B—Invite applicants to roundtable discussions (not the Tuesday staff
meetings). Previous PAT recommended
implementing 5-B-1 and 5-B-2 instead of 5-B.
·
Recommendation
#5-B-1—Site Plan Meeting. Has been
implemented.
·
Recommendation
#5-B-2—Roundtable Meeting. Has not been
implemented.
·
Recommendation
#5-C—“Reward” (speed up) well done submittals over poorly done ones. Has not been implemented.
·
Recommendation
#5-D—Keep first come/first served basis.
Separate large from small. Was to
be determined by BHZ, not sure if it was implemented.
·
Recommendation
#5-E—Small jobs take two weeks maximum for review, with phone call if
incomplete. The definition of a small
job has changed. It used to mean no
stormwater management, but now almost everything has stormwater management.
·
Recommendation
#5-F—Standard letter of rejection, to save comment letter time. Has been implemented.
·
Recommendation
#5-G—Need stricter rejection process. Is
not always followed.
·
Recommendation
#5-H—Bill for subsequent submittals, with fees known in advance, and check due
at re-submittal. Has not been
implemented.
·
Recommendation
#5-I—Remove billing from hands of reviewer.
Has not been implemented.
·
Recommendation
#5-J—Submittal dates for transfer of properties established without regard to
subdivision plat review and process. Not
really a problem anymore.
·
Recommendation
#5-K—Clear corporate limit lines on plans would be helpful. Has been implemented.
·
Recommendation
#5-L—Comprehensive plans to be submitted as sketch plans. Has not been implemented.
·
Recommendation
#5-M—Deal with size of plans...takes days to reduce size for Public Works. Has not been implemented.
·
Recommendation
#6—Modify Department’s Checklist. Has
not been implemented.
·
Recommendation
#6-A—Delete #25 (as-builts). Has not
been done.
·
Recommendation
#6-B—Delete #33 (detailed sequence of construction). Has not been done.
·
Recommendation
#6-C—Delete #36 (construction specifics)
Has not been done.
·
Recommendation
#6-D—Delete #9 (property monument) Has
not been done.
·
Recommendation
#6-E—Delete #10 (deed and plat reference)
Has not been done.
·
Recommendation
#6-F—Divide into 2 sections: necessary
and original submittal versus later in process.
Has not been done.
·
Recommendation
#6-G—#28 Most often missed. Has not been
done.
·
Recommendation
#7—Fire Marshall to attend all Tuesday morning meetings, unless told not
necessary. Has not been implemented.
·
Recommendation
#8—Invite John Redden (County Public Works Department) to the Tuesday meeting,
unless not necessary. Can John Redden
coordinate the fire department approval process to speed it up? Has been implemented.
·
Recommendation
#9—Hire consultants with money currently in the budget to do City drainage
plan. Has been implemented
·
Recommendation
#10—Hire consultants with money currently in the budget to do plan of potential
annexation areas. Has not been
implemented.
·
Recommendation
#11—Education of the private sector/ Announcement of fees for the year. Has not been implemented.
·
Recommendation
#12—Coordination of Stormwater Management software between City departments and
private sector to save time. City now
accepts any software, so this is no longer a problem.
·
Recommendation
#13—Public Works would like to require dates for responses from other
departments. John Pick was to follow up
on this.
·
Recommendation
#14—City and
·
Recommendation
#15—Need a single sheet listing all people needed for various approvals. Dale was not sure if this has been
implemented.
·
Recommendation
#16—Easement requirement: want plat only
and no deed (like the County) (P. Wilbur).
Has not been implemented.
·
Recommendation
#17—Small Permit Day once a week for BHZ applications. Was to be implemented by BHZ director.
·
Recommendation
#18—Meeting of City, County, Developers, and all agencies for plan
submittals. Has not been implemented.
·
Recommendation
#19—Support formal pre-annexation agreements.
Has been implemented.
·
Recommendation
#20—Annexation-County to pre-designate areas open for annexation. Change to coincide with County zoning
changes. Dale was not sure if this has
been implemented.
·
Recommendation
#21—Have approval for City and County Stormwater Management under review
authority of Planning and Zoning for all City/County facilities with exception
that public storm drain construction in City streets would be under their
individual jurisdiction. Has not been
implemented.
·
Recommendation
#22—Change from service area assessment to front foot assessment (into revolving
fund). Has not been implemented.
6. Matt Drew
began discussion on how to go about implementing the plan. David Bates said that one of the biggest
problems with the PAT Recommendation Plan last time was that there was no
follow-up. Brock Parker suggested
continuing to have meetings once the plan is established. He recommended going from weekly to monthly
meetings to check with everyone to see how the plan is working.
David said
that some parts of the plan won’t be able to be decided by Dale and John
Jacobs; some things will have to go through City Council. The recommendations that the team makes need
to be taken seriously and followed-up with.
There also should be a date that each item is to be implemented by,
which should be followed to make sure it happens.
7. The next
meeting has been scheduled for Tuesday, December 12, 2006 at 4:00 in Room 300.